Project Summary

 

 

4 Number concrete frames rising 9 to 11 storeys consisting of 25,000 m² of slabs

& 4 nr cores to be completed in 20 weeks.

Project Task

Plot N14 - Completion of 4 number 9 to 11 storey concrete frames. Each block consisting of 600m.sq of slab per level with 1 core per block.

 

Project Value

£2.0 million (Labour & Formwork only – excludes supply of concrete, Rebar & Crane-age)

 

Programme

Tender programme - 20 weeks – actual completed programme – 20 weeks

 

Challenges

Achieving programme with the use of only two tower cranes servicing all trades.

 

Logistics of materials to and from site for security reasons, all deliveries had to be booked 24 hours in advance

 

Small footprint of Plot N14 meant that all deliveries

had to be ‘just in time’ with no capacity for storage

on site.

 

Working weekends, early mornings and late

evenings to achieve programme deadline.

 

Internal formwork to cores had to be high quality

with an exposed to view finish.

Facebook logo Twitter logo LinkedIn logo

All enquiries to:

Tel : (+44) 28 7122 9220   Email : info@glenform.co.uk

Website Design and Development by Rotate Design™

Copyright © 2019 GLENFORM CONSTRUCTION Ltd. All rights reserved.